COMPLETED PROJECTS
Turnkey Solutions
Pressure Vessels, Tanks and Equipment
PRECAUTIONARY MEASURES – FOR TANKS, MIXTURES & AGITATORS
- All Qualified Weldors To Be Used For Tank Fabrication Duly Qualified Through Wps, Pqr & Wpq – Welding Procedure As Per Asme Section Ix.
- Pmi To Be Done Before Dispatch For Double Confirmation Of Finished Goods To Client. In Addition To Mtc & Lab Report Verification Through Mir & Mrir.
- Extra Precaution Of Mill Finish Material From Scratches During Fabrication, We Will Use Pvc Coated Material.
- Dp To Be Done To Ensure The Crack Free Welding.
- Radiography To Be Done On Welded Portion To Avoid The Defective Welding Quality.
- Hydro Test To Be Done To Check Any Kind Of Leakage.
- Welded Portion To Be Band Polished For Welding Identification And Free From Black Marks.
Civil & Structure
Process and Utility Piping
PRECAUTIONARY MEASURES – FOR PROCESS & UTILITY PIPING SYSTEM
- All Qualified Weldors To Be Used For Piping System Duly Qualified Through Wps, Pqr & Wpq – Welding Procedure As Per Asme Section 31.3 .
- Pmi To Be Done Before Dispatch Pre Fabricated Process Piping And Raw Material Of Utility Piping, Double Confirmation Of Finished Goods To Client. In Addition To Mtc & Lab Report Verification Through Imir.
- We Are Purchasing Process Piping Like Ss-316 Tubing And Fitting And Pfa Tubing With Fitting Duly Fda Approved, Which Is Additional Features In Our Procurement Quality Point Of View (High Quality Standard).
- Dp To Be Done To Ensure The Crack Free Welding.
- Hydro Test To Be Done To Check Any Kind Of Leakage.
- Radiography To Be Done On Welded Portion To Avoid The Defective Welding Quality.
- Welded Portion To Be Band Polished For Welding Identification And Free From Black Marks.
HVAC
Electrical
Instrumentation
Insulation
Mane India Private Limited
PROJECT DEATILS
- Project: Flavour and Fragrance
- Approximate Cost in Crores: 25 Crores
- Delivery to Commissioning period: from November 2019 to December 2020
Merino Industries Limited
PROJECT DEATILS
- Project : Plant of Engineered Ply
- Approximate Cost in Crores : 45 Crores
- Delivery to Commissioning period : from April 2022 to August 2023
Alkyl Amines Chemicals Limited
PROJECT DEATILS
- Project : Manufacturing of Storage Tan, Pressure Vessel etc for Various Project
- Approximate Cost in Crores : 15 Crores
- Delivery to Commissioning period : Continuous
Durr India Private Limited
PROJECT DEATILS
- Project : Equipment for Paint Shop for Various Project
- Approximate Cost in Crores : 40 Crores
- Delivery to Commissioning period : Continuous
Hindalco Industries Limited
PROJECT DEATILS
- Project : Bio-mass
- Approximate Cost in Crores : 6 Crores
- Delivery to Commissioning period : June 2021 to June 2022
Hindalco Industries Limited
PROJECT DEATILS
- Project : Varun
- Approximate Cost in Crores : 42 Crores
- Delivery to Commissioning period : June 2023 (Work in Progress)
MARS International India Private Limited
PROJECT DEATILS
- Project : Galaxy
- Approximate Cost in Crores : 25 Crores
- Delivery to Commissioning period : August 2020 to March 2022
Pune Maha Metro
PROJECT DEATILS
- Project : Elevated Metro Station
- Approximate Cost in Crores : 15 Crores
- Delivery to Commissioning period : August 2020 to November 2021
Thermax Onsite Energy Solutions Limited
PROJECT DEATILS
- Project : Biocon Limited
- Approximate Cost in Crores : 6 Crores
- Delivery to Commissioning period : April 2022 to March 2023
Toyo Ink India Private Limited
PROJECT DEATILS
- Project : PU and Hardner Plant
- Approximate Cost in Crores : 5 Crores
- Delivery to Commissioning period : December 2020 to November 2021