COMPLETED PROJECTS
Turnkey Solutions
![](https://truetechvision.com/wp-content/uploads/2023/01/4-10-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/2-5-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/5-2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/Untitled-design-68-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/3-11-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/2-4-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/Untitled-design-67-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/Untitled-design-47-250x300.png)
Pressure Vessels, Tanks and Equipment
![](https://truetechvision.com/wp-content/uploads/2023/01/tank3-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/1-5-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/tank2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/tank1-250x300.png)
PRECAUTIONARY MEASURES – FOR TANKS, MIXTURES & AGITATORS
- All Qualified Weldors To Be Used For Tank Fabrication Duly Qualified Through Wps, Pqr & Wpq – Welding Procedure As Per Asme Section Ix.
- Pmi To Be Done Before Dispatch For Double Confirmation Of Finished Goods To Client. In Addition To Mtc & Lab Report Verification Through Mir & Mrir.
- Extra Precaution Of Mill Finish Material From Scratches During Fabrication, We Will Use Pvc Coated Material.
- Dp To Be Done To Ensure The Crack Free Welding.
- Radiography To Be Done On Welded Portion To Avoid The Defective Welding Quality.
- Hydro Test To Be Done To Check Any Kind Of Leakage.
- Welded Portion To Be Band Polished For Welding Identification And Free From Black Marks.
![](https://truetechvision.com/wp-content/uploads/2023/01/Untitled-design-5.png)
Civil & Structure
![](https://truetechvision.com/wp-content/uploads/2023/01/civil1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/civil3-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/civil2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/civil4-250x300.png)
Process and Utility Piping
![](https://truetechvision.com/wp-content/uploads/2023/01/pipe3-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/pipe4-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/pipe1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/pipe2-250x300.png)
PRECAUTIONARY MEASURES – FOR PROCESS & UTILITY PIPING SYSTEM
- All Qualified Weldors To Be Used For Piping System Duly Qualified Through Wps, Pqr & Wpq – Welding Procedure As Per Asme Section 31.3 .
- Pmi To Be Done Before Dispatch Pre Fabricated Process Piping And Raw Material Of Utility Piping, Double Confirmation Of Finished Goods To Client. In Addition To Mtc & Lab Report Verification Through Imir.
- We Are Purchasing Process Piping Like Ss-316 Tubing And Fitting And Pfa Tubing With Fitting Duly Fda Approved, Which Is Additional Features In Our Procurement Quality Point Of View (High Quality Standard).
- Dp To Be Done To Ensure The Crack Free Welding.
- Hydro Test To Be Done To Check Any Kind Of Leakage.
- Radiography To Be Done On Welded Portion To Avoid The Defective Welding Quality.
- Welded Portion To Be Band Polished For Welding Identification And Free From Black Marks.
![](https://truetechvision.com/wp-content/uploads/2023/01/Untitled-design-5.png)
HVAC
![](https://truetechvision.com/wp-content/uploads/2023/01/hvac1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/hvac2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/hvac3-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/hvac4-250x300.png)
Electrical
![](https://truetechvision.com/wp-content/uploads/2023/01/electrical1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/electrical2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/electrical4-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/electrical3-250x300.png)
Instrumentation
![](https://truetechvision.com/wp-content/uploads/2023/01/Instrumentation2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/Instrumentation3-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/Instrumentation1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/Instrumentation4-250x300.png)
Insulation
![](https://truetechvision.com/wp-content/uploads/2023/01/insulation1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/insulation2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/insulation3-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2023/01/insulation4-250x300.png)
Mane India Private Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/4-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/3-1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/2-1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/1-1-250x300.png)
PROJECT DEATILS
- Project: Flavour and Fragrance
- Approximate Cost in Crores: 25 Crores
- Delivery to Commissioning period: from November 2019 to December 2020
Merino Industries Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/8-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/7-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/6-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/5-250x300.png)
PROJECT DEATILS
- Project : Plant of Engineered Ply
- Approximate Cost in Crores : 45 Crores
- Delivery to Commissioning period : from April 2022 to August 2023
Alkyl Amines Chemicals Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/12-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/11-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/10-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/9-250x300.png)
PROJECT DEATILS
- Project : Manufacturing of Storage Tan, Pressure Vessel etc for Various Project
- Approximate Cost in Crores : 15 Crores
- Delivery to Commissioning period : Continuous
Durr India Private Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/14-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/15-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/16-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/13-250x300.png)
PROJECT DEATILS
- Project : Equipment for Paint Shop for Various Project
- Approximate Cost in Crores : 40 Crores
- Delivery to Commissioning period : Continuous
Hindalco Industries Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/18-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/19-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/20-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/17-250x300.png)
PROJECT DEATILS
- Project : Bio-mass
- Approximate Cost in Crores : 6 Crores
- Delivery to Commissioning period : June 2021 to June 2022
Hindalco Industries Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/24-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/22-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/21-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/23-250x300.png)
PROJECT DEATILS
- Project : Varun
- Approximate Cost in Crores : 42 Crores
- Delivery to Commissioning period : June 2023 (Work in Progress)
MARS International India Private Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/28-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/Untitled-design2-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/Untitled-design-1-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/Untitled-design-250x300.png)
PROJECT DEATILS
- Project : Galaxy
- Approximate Cost in Crores : 25 Crores
- Delivery to Commissioning period : August 2020 to March 2022
Pune Maha Metro
![](https://truetechvision.com/wp-content/uploads/2024/01/33-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/32-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/31-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/30-250x300.png)
PROJECT DEATILS
- Project : Elevated Metro Station
- Approximate Cost in Crores : 15 Crores
- Delivery to Commissioning period : August 2020 to November 2021
Thermax Onsite Energy Solutions Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/37-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/36-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/35-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/34-250x300.png)
PROJECT DEATILS
- Project : Biocon Limited
- Approximate Cost in Crores : 6 Crores
- Delivery to Commissioning period : April 2022 to March 2023
Toyo Ink India Private Limited
![](https://truetechvision.com/wp-content/uploads/2024/01/41-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/40-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/39-250x300.png)
![](https://truetechvision.com/wp-content/uploads/2024/01/38-250x300.png)
PROJECT DEATILS
- Project : PU and Hardner Plant
- Approximate Cost in Crores : 5 Crores
- Delivery to Commissioning period : December 2020 to November 2021